Dharmadhara shrine room update

Drew reports that "the shrine room is nearly there and is looking great. We'll be doing a few more things before the retreats in April: put extra fire-resistant treatment on the outside (required by code), add trim at wall/floor, and add lighting. We were running short on the dried boards we cut earlier so we prioritized the walls and floor. This means the following things will be finished later: add doors to shelves, finish wall behind shelves, and add boards to the clear story (short wall up in the ceiling). We've already milled the boards for that but they'll take a few months to dry."